Coordinates: 24°52′20″N 75°36′50″E / 24.87222°N 75.61389°E / 24.87222; 75.61389

Rajasthan Atomic Power Station

From Wikipedia, the free encyclopedia
Jump to navigation Jump to search

Rajasthan Atomic Power Station
Lua error in Module:Infobox_mapframe at line 197: attempt to index field 'wikibase' (a nil value).
CountryIndia
CoordinatesLua error in Module:Coordinates at line 489: attempt to index field 'wikibase' (a nil value).
Construction began1963
Commission date16 December 1973
OperatorNuclear Power Corporation of India Ltd (NPCIL)
Nuclear power station
Reactors8
Reactor typePHWR
Reactor supplierUnits 1 & 2: AECL
Units 3 to 8: NPCIL
Cooling towers8 × Natural Draft
Cooling sourceRana Pratap Sagar Dam, Chambal River
Power generation
Lua error in Module:Infobox_power_station at line 110: attempt to index field 'wikibase' (a nil value).
Nameplate capacity1780 MW
Capacity factor78.07% (2020-21), Unit 1:17%, Unit 2:57 %, Unit 3 to 6:77 % approx[1]
Annual net output6810.61 GWh (2023-24)(units 1 to 6)
External links
WebsiteNuclear power Corporation of India Ltd

The Rajasthan Atomic Power Station (RAPS; also Rajasthan Atomic Power Project - RAPP) is a nuclear power plant located at Rawatbhata in the state of Rajasthan, India. It is the third largest nuclear power plant in the country after the Kudankulam Nuclear Power Plant and Kakrapar Atomic Power Station in terms of installed capacity.

History

[edit | edit source]
File:Rawatbhata Nuclear Powerplant.jpg
Rawatbhata Nuclear Powerplant

The construction of the Rajasthan Atomic Power Project (RAPP) began in 1963 with two CANDU (Canada Deuterium Uranium) pressurised heavy water reactor (PHWR) capable of producing 220 MW of electricity each. Ten years later, in 1973 RAPS-1 was put into service. In 1974 after India conducted Smiling Buddha, its first nuclear weapons test, Canada stopped its support of the project, delaying the commissioning of RAPS-2 until 1981.[2]

Unit 1:In the early 1960s, Indian Department of Atomic Energy (DAE), and Canada's Atomic Energy of Canada limited AECL signed an MoU to build two reactors of 200 MW each. Construction began in 1963 and unit 1 achieved operational status in 1973. Since the beginning, it faced several technical issues such as cracks in the end shields, leak of the moderator, rupture of fuel channel, etc. To alleviate these issues it was derated to 100MWe. But issues continued to occur. The unit had low capacity factor, low availability and caused economic losses. Due to these issues and safety concerns, it was put in a permanent shutdown in October 2004.

Unit 2: When India conducted the 1974 Nuclear tests at Pokhran in Rajasthan, Canada withdrew from the project, leaving the DAE alone to develop the second reactor. Learning lessons from unit 1, and with help of other industries such as Bharat heavy electricals limited BHEL and L&T the reactor was completed and put into operation in 1981. It lacked many of the issues that had plagued Unit 1, yielding a capacity factor of 67.2% compared to Unit 1's 21.1% and continues to operate through 2024.

In the context of the Indian atomic program, two more PHWR with an output of 220 MW each were built. They cost around 570 million dollars. RAPS-3 became critical on 24 December 1999, RAPS-4 became critical on 3 November 2000. Commercial operations began on 1 June 2000 for unit 3, and on 23 December 2000 for unit 4.

Two more reactors (RAPS-5 and RAPS-6) with 220 MWe have also been built, with unit 5 beginning commercial operation on 4 February 2010, and unit 6 on 31 March 2010.[3]

One of the new Indian-designed 700 MWe series of the reactor (RAPP-8) is under construction in Rajasthan. One (RAPP-7) was recently commissioned in April 2025.

In November 2012, the International Atomic Energy Agency (IAEA) intensively audited over several weeks two reactors at the Rajasthan Atomic Power Station for safety. It has been concluded that the reactors are among the best in the world, the indigenously made 220 MW atomic plants can withstand a Fukushima type of accident, even suggesting that the "safety culture is strong in India" and that India emerged a winner with a high global safety rank.[4]

First concrete for unit 7 was poured on 18 July 2011,[5] with commercial operation expected by 2016. First concrete for unit 8 was poured on 30 September 2011. Unit 7 and unit 8 will cost together an estimated Rs 123.2 billion (US$2.6 billion).[6]

In 2024 the AERB granted permission for unit 7 fuel loading and addition of moderator. The 19 September 2024, unit 7 started a controlled fission chain reaction.[7]

In March 2025 unit 7 at Rajasthan site was connected to the grid. It is the 3rd 700 MWe indigenous pressurized heavy water reactor connected to the grid. It entered commercial operations in April of 2025.[8]

Incidents

[edit | edit source]

By 2003 RAPS-1 had experienced numerous problems due to leaks, cracks in the end-shield and turbine blade failures, had undergone repairs and appeared to be generating 100 MW of electricity, with RAPS-2 reportedly generating 200 MW.[2] Unit 1, due to its issues, technical and economic unviability, was decided to place into a permanent shutdown state in October 2004. It is the only unit owned by the Department of Atomic Energy.

On 29 August 2006, a 90% iron meteorite weighing 6.8 kilograms (15 lb) fell in Kanvarpura village, near the power station. The Deputy Director-General (western region) of the Geological Survey of India, R.S. Goyal, said that devastation on an "unimaginable scale" would have ensued had the object struck the station.[9] However, the kinetic energy of a meteorite of this size is smaller than that of jet aircraft frequently used as a basis for impact resistance of containment structures.[10][11]

In June 2012, 38 workers were exposed to tritium when a welding operation went wrong inside the protected environment of the reactor.[12]

Units

[edit | edit source]
Phase Unit
No.
Reactor Status Capacity in MWe Construction start First criticality Grid Connection Commercial operation Closure Notes
Type Model Net Gross
I 1 PHWR CANDU Shut Down-pending decommissioning 90 100 1 August 1965 11 August 1972 30 November 1972 16 December 1973 9 October 2004 [13]
2 PHWR CANDU Operational 187 200 1 April 1968 8 October 1980 1 November 1980 1 April 1981 [14]
II 3 PHWR IPHWR-220 Operational 202 220 1 February 1990 24 December 1999 10 March 2000 1 June 2000 [15]
4 PHWR IPHWR-220 Operational 202 220 1 October 1990 3 November 2000 17 November 2000 23 December 2000 [16]
III 5 PHWR IPHWR-220 Operational 202 220 18 September 2002 24 November 2009 22 December 2009 4 February 2010 [17]
6 PHWR IPHWR-220 Operational 202 220 20 January 2003 23 January 2010 28 March 2010 31 March 2010 [18]
IV 7 PHWR IPHWR-700 Operational 630 700 18 July 2011 19 September 2024 17 March 2025 15 April 2025 [19][20][21]
8 PHWR IPHWR-700 Under Construction 630 700 30 September 2011 [19][22]

Current status

[edit | edit source]

Unit 1 was placed under permanent shutdown and is to be decommissioned. Units 2 through 6 are currently operational.

Unit 7 achieved criticality on 19 September 2024. On 17 March 2025, RAPS 7 was connected to the grid for the first time. This step was taken after clearance from the AERB. It came online for commercial operation on 15 April 2025.

See also

[edit | edit source]

Lua error in mw.title.lua at line 392: bad argument #2 to 'title.new' (unrecognized namespace name 'Portal').

References

[edit | edit source]
  1. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  2. ^ a b Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  3. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  4. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  5. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  6. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  7. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  8. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  9. ^ Meteorite fall in Rajasthan village The Hindu, 6 September 2006.
  10. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  11. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  12. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  13. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  14. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  15. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  16. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  17. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  18. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  19. ^ a b Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  20. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  21. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
  22. ^ Lua error in Module:Citation/CS1/Configuration at line 2172: attempt to index field '?' (a nil value).
[edit | edit source]

Lua error in Module:Authority_control at line 153: attempt to index field 'wikibase' (a nil value).